Advertisement

Camp Humphreys housing complex behind schedule

Two Pyongtaek apartment towers now set for 2006-07 completion

PYONGTAEK, South Korea — Construction will be finished later than expected on a family housing complex at Camp Humphreys in South Korea, planners say.

Plans call for a three-building housing complex with an underground garage, picnic areas and playgrounds at a projected cost of $40.7 million. The first building, five stories tall, was finished in September 2003.

But two eight-story apartment towers, a garage and outdoor recreation areas have snags causing completion delays of four to 16 months, said Brandi Dennis-Peña, project engineer with the U.S. Army Corps of Engineers’ Far East District Pyongtaek Resident Office at Camp Humphreys.

An April 2006 completion date for one of the two towers is about four months beyond the original plan. And the other tower now is set for a May 2007 completion, about five months later than planned.

The two-level, 220-space garage now is to be finished by April 2006, about 16 months past the initial December 2004 target date.

Causing the delays were several factors, including complications that arose in laying foundation piles, the need to relocate sewer and communication lines and a building that housed AM/FM antennas, Dennis-Peña said. Also, land on which the central utilities plant for apartment towers is to be built currently is the site of another building still in use. Base officials first must relocate occupants so the building can be demolished, she said.

“For the central utility plant, essentially, we could finish the structure of the building for the tower,” she said. “However, we would not be able to run, say, the mechanical, which would encompass water, electrical.”

She said she was told at a meeting Tuesday that the occupants in the building to be razed might be relocated “quite soon.”

The two towers will be identical, each with 48 apartments and three elevators running to the below-ground garage. Residents of the existing five-story building will walk from their lobby to a street-level elevator to the garage.

The complex is one of numerous projects for expanding Camp Humphreys into its future role as the U.S. military’s largest installation in South Korea.

Under plans worked out between South Korea and the United States, U.S. forces in and north of Seoul would relocate to the installation. By 2008 it is to serve as headquarters for U.S. Forces Korea and other commands.


Advertisement
Advertisement
Advertisement

Your Photos on Stripes Spotted

  • 2013 USO JAPAN CHARITY GOLF TOURNAMENT
  • Independent News and Information Since 1942
  • Troops at Camp Arifjan Compete in Fitness Events